Solar Installation in West Virginia
Licensed in West Virginia
Earth Right holds West Virginia Contractor Licence WV064401. We are based at 52 Beechwood Drive in Lynchburg, Virginia, and our crews travel into West Virginia for solar and battery work.
Most solar pages tell you what solar could save you. This one tells you how the process actually works in West Virginia, because that is where projects get delayed and it is the part almost nobody explains up front.
The federal tax credit has ended, and West Virginia has no state replacement
How Appalachian Power Interconnection Actually Works
Everything in this section comes from Appalachian Power’s own West Virginia Net Metering Customer Information Guide, revision v2.0, effective 1 February 2026. Net metering arrangements and interconnection standards in West Virginia are governed by the Legislative Rule at Title 150CSR33.
Two Interconnection Levels
Level 1 covers systems with a nameplate capacity of 25 kW or less that use inverter-based, non-islanding, UL listed and certified equipment, connecting to distribution facilities operating at 69 kV or less. The application fee is $30.
Level 2 covers anything that does not qualify as Level 1, including systems above 25 kW or those not meeting the Level 1 equipment and voltage conditions. The application fee is $50 plus $1 per kW of capacity.
System Size Limits
The maximum generator size on the alternating current side is 25 kW for a residential account, 500 kW for commercial and 2 MW for industrial.
What You Have to Supply
- A completed interconnection application, submitted through the AEP PowerClerk portal
- Proof of general liability insurance with a minimum of $100,000. You must carry it for as long as you stay interconnected.
- An electrical one-line diagram and a site diagram
- Generator and inverter specification sheets showing UL 1741-SB compliance
The Equipment Requirement People Forget
A labelled, lockable, visible load break disconnect is required outside, near your electric meter, so the generator can be isolated if necessary. This is not optional and it affects where equipment sits on the house. We plan for it at design rather than discovering it at inspection.
Inspection
Every installation gets an electrical inspection, carried out either by your local authority having jurisdiction or by a third-party electrical inspector licensed by the State of West Virginia.
The connection type matters. A supply-side connection, ahead of the service disconnect, counts as a modification of your existing service, so the inspection covers the service entrance as well as the solar equipment, and a modified service has to meet the standard of a new installation. That can mean panel work you were not expecting. We tell you which of the two your house needs before you sign.
Turning It On
After installation you complete conformance testing under IEEE 1547 and notify Appalachian Power. You then submit a Certificate of Completion signed by the inspector, along with photographs. Appalachian Power reviews the submissions, installs or reprograms a bi-directional meter, and issues Permission to Operate. Each of those stages carries a ten business day window on their side.
Until Permission to Operate is issued, your generator stays switched off. Appalachian Power is explicit about this and so are we, because switching on early is the fastest way to create a problem. Terms, fees and eligibility for net metering are subject to revision by the West Virginia Public Service Commission, so we check the current guide before every quote rather than relying on what was true last year.
What We Install
- Residential solar, roof and ground mounted.
- Commercial solar.Â
- Battery backup, including Tesla Powerwall and SolarEdge storage.Â
- Detach and reset, taking an existing array off for a roof replacement and putting it back.
- Service and repair on existing systems, including systems we did not install
- EV charger installation.
- Energy efficiency work: insulation, air sealing and attic ventilation.
Every item on that list is done by our own crews under WV064401. Nothing gets handed to a subcontractor you have never met.
Credentials You Can Check
Class A Virginia Contractor with AES, CBC, RBC and ELE designations
Certified SolarEdge Installer, plus Certified Home Battery Technician, Certified Energy Hub Technician and Certified Commercial Installer
Tesla Powerwall Channel Training certified
Certified PWRcell Installer
Building Performance Institute Certified Professional and Certified Building Analyst
Question West Virginia Homeowners Ask
Yes. West Virginia Contractor Licence WV064401.
Not for homeowners. Section 25D expired on 31 December 2025.
No state tax credit or rebate. Net metering is the mechanism.
Appalachian Power’s guide sets the maximum generator size at 25 kW AC for a residential account.
Yes. Appalachian Power requires proof of general liability insurance with a minimum of $100,000, and you carry it for as long as the system stays interconnected.
Not until Appalachian Power issues Permission to Operate, after inspection, document review and the meter exchange. Several stages carry ten business day windows on their side. We will give you a realistic date rather than a hopeful one.
Not on its own. A grid-tied system shuts down during an outage for the safety of line workers. Battery storage with a transfer switch is what keeps the house running, and it is worth discussing at design.